November 2025 Updates
Sephardic Beit Midrash

Renovations for the Sephardic Beit Midrash are progressing smoothly. We are currently installing new flooring and ceiling tiles and finalizing the design of the decorative windows. We anticipate that all of the custom woodwork from Israel which includes the Aron Kodesh, Shulchan, bookshelves, and Mechitza, will be installed over the January break.
Mechina Beit Midrash
Carpeting has now been installed in the Mechina Beit Midrash, and a committee of teachers is currently meeting to select sefarim for the new library.
Turf Field
We have interviewed several vendors for the installation of our new turf field. In addition, electrical permits are currently being secured so we can reconfigure the lighting to accommodate a properly sized flag football and soccer field.
Perimeter Fencing
Perimeter fencing has now been installed around the campus, along with new guard booths. Swing gates are currently being manufactured and will be installed in the near future along with new cameras, alarms, and access-control systems that will further enhance the safety and security of our students and faculty.